Results for "Phu Bai International Airport Terminal"
Result 1 - 10 in 5
Cập Nhật 09-02-2022
Although 2021 witnessed various unfavorable weather conditions and the COVID-19 pandemic, the project investor has made effort to urge establishments and construction contractors to speed up the progress in their possible conditions.
Tag: construction, T2 Terminal, Phu Bai International Airport, COVID-19 pandemic, complete on schedule, effort, December 2022, electromechanical house
Cập Nhật 30-03-2021
And my dream came true, with many flights to big provinces and cities across the country and most of the airlines. During the flight journey, there were many interesting experiences.
Tag: flight, Viettravel Airlines, Phu Bai Airport, Hue, development step of Hue tourism, Phu Bai International Airport Terminal
Cập Nhật 30-12-2019
Construction project of Passenger Terminal T2 of Phu Bai International Airport is invested by Vietnam Airport Corporation with a total investment capital of VND 2,250 billion.
Tag: Commencement of construction, Passenger Terminal T2, Phu Bai International Airport, Vietnam Airport Corporation
Cập Nhật 09-07-2018
The total investment capital of the project is around VND 1,700 billion from the development investment capital of ACV; the terminal T2 is expected to be built within 18 months.
Tag: Passenger Terminal T2, Phu Bai International Airport, land handover, Airports Corporation of Vietnam (ACV)
Cập Nhật 24-06-2018
According to the plan, Phu Bai International Airport will be expanded with a total investment of about 5,560 VND billion on the terminals, the runways and the aircraft stands…
Tag: Phu Bai international Airport, expansion, 5, 560 VND billion