Construction of Thuan An sea-crossing bridge throughout the National Day holiday

TTH.VN - During the holidays, hundreds of engineers and workers were still working hard throughout the National Day holiday on the Thuan An sea-crossing bridge (Hue City).

Being at the construction site of the bridge over the Huong River on Nguyen Hoang StreetTelling stories of heritage on Ao daiThe traces of Can Chanh PalaceHue City: Focusing on public investment to speed up economic and social developmentJICA sponsors nearly 260 billion VND for the construction of the walking path along the Nhu Y River

On the morning of September 3, Mr. Nguyen Nam Tung, Commander of Dat Phuong Group Joint Stock Company, participating in the construction of the Thuan An sea crossing bridge project, said that the construction continued throughout the holiday contributing to ensuring that the main bridge piers in the middle of the sea and the bridge girders on the shore were completed on schedule by the end of 2023. However, it is difficult to clear the ground in Hai Duong commune, so we hope that the relevant departments and agencies will soon pay attention to solving the problem so that the contractors can accelerate the progress of items on the road leading to the bridge. With such total coordination, the Thuan An sea-crossing bridge project can be technically opened to traffic at the end of October 2024 and completed in March 2025 as originally planned.

The project of coastal road and Thuan An sea-crossing bridge has a total investment (phase 1) of VND 2,400 billion, implemented with a period of 3 years. The scale of the route is 7,785m long; in which, the bridge section is about 2.36km long, starting from Tam Giang bridge to Thuan An sea-crossing bridge and ending at the intersection of National Highway 49A – National Highway 49B in Thuan An Ward (Hue City).

Below are some pictures on the construction site:

Dat Phuong contractor mobilizing more than 100 engineers, workers and many vehicles to construct bridge foundation piers in Thuan An coastal area.  
Construction of bridge pier T27 in the middle of the sea 
Workers of Dat Phuong contractor preparing the bridge girder work at Thuan An bank.  
Engineers and workers of Tan Nam contractor participating in the construction of the main foundation pier in the middle of the sea. 
 
 Tan Nam contractor mobilizing many machines and human resources to construct the foundation pier in the coastal area of Hai Duong commune
By Song Minh
RATING
Be the first to review this post!
  Comment

YOU MAY CARE ABOUT

Contemporary bamboo in construction

Once following a friend of mine to Hoi An (Quang Nam province), I was quite impressed with the communal house of Cam Thanh commune. From outside, the building has a bold characteristic of the image of a Vietnamese village with a row of upright areca palm trees. In particular, the structure of sturdy wooden columns and bamboo frames, and available natural materials make visitors feel close to their homeland.

Contemporary bamboo in construction
Aspiration from Thuan An sea-crossing bridge

For more than a year, the fact that the bridge over Thuan An sea mouth was constructed has always been a topical issue in Thua Thien Hue. Everywhere I went, people excitedly talked about building a bridge, and in the future, their hometown will have a bridge across the sea at the top of the Central region.

Aspiration from Thuan An sea-crossing bridge
Overall construction of public transport system

On the afternoon of August 11, Chairman of the Provincial People's Committee Nguyen Van Phuong had a meeting with KRRI Group on the research and implementation of green traffic projects in Thua Thien Hue.

Overall construction of public transport system
Return to top